How deep should a patio sub-base be?

Last reviewed 1 July 2026

Short answer

100 mm of compacted sub-base for a pedestrian patio on firm ground, 150 mm over soft or clay subsoil, and 150–200 mm where vehicles will cross. Order about 30% more loose material than the compacted depth — a 100 mm compacted layer over 20 m² needs roughly 2.6 m³ of loose Type 1, not 2 m³.

Work it out for your project with the patio and paving calculator

Depth by use and ground

Compacted sub-base depth
UseFirm subsoilSoft or clay subsoil
Footpath75–100 mm100–150 mm
Patio, pedestrian only100 mm150 mm
Patio with occasional light vehicle150 mm200 mm
Car driveway150 mm200 mm
Driveway with delivery vehicles200 mm250 mm or designed

Depths are of compacted material, measured after whacking down.

The compaction allowance

MOT Type 1 and equivalent dense graded bases lose roughly a quarter to a third of their loose volume when compacted. The standard working figure is a factor of 1.3.

So a 100 mm compacted layer needs about 130 mm of loose material spread before compaction. Across 20 m² that is 2.6 m³ loose, which at 2,000 kg/m³ is about 5.2 tonnes — six UK bulk bags rather than the four you would order from the compacted volume.

This is the single most common reason a sub-base order comes up short.

loose volume = area × compacted depth × 1.3

Laying it properly

  1. Excavate to a firm, undisturbed formation. Remove all topsoil and organic material — it will rot and settle.
  2. If the formation is soft or wet, consider a geotextile separator so the sub-base is not pumped into the subgrade.
  3. Spread in layers of no more than 100 mm. A plate compactor cannot compact more than that in one pass.
  4. Compact each layer until the surface stops moving under the plate — typically three or four passes in different directions.
  5. Check levels and falls as you go. A patio should fall about 1:80 away from the building.
  6. Blind the surface with a thin layer of grit or sharp sand if it is too coarse to screed the bedding onto.

Working out the excavation

Total dig depth is the sub-base depth plus the bedding depth plus the slab thickness. For a typical patio that is 100 + 40 + 35 = 175 mm below the finished paving level.

Remember the finished level must be at least 150 mm below the damp-proof course of any adjoining building.

The spoil has to go somewhere. Excavating 175 mm over 20 m² produces about 3.5 m³ of soil, which is roughly 4.5 tonnes and a full builders' skip.