Count slabs or pavers including joint widths, then size the sub-base, bedding mortar, jointing compound and edge restraints for the whole build-up.

Estimate updated. 60 paving slabs of 600 mm × 600 mm paving slabs required.

Estimate results

How this calculator works

Every figure below is derived rather than looked up, so you can check it against your own numbers. Nothing is hidden behind a black box.

Unit count

Paving is counted by module, not by slab. A 600 × 600 mm slab with a 10 mm joint occupies a 610 × 610 mm module, so it covers 0.3721 m² rather than 0.36 m².

Ignoring the joint over-orders by about 3% on a 10 mm joint and by more on small units — which is why block paving calculations go wrong most often.

units = area ÷ ((unit length + joint) × (unit width + joint))

Pattern and waste

Each pattern carries a recommended minimum waste allowance: 5% for a straight grid, 7% for running bond, 10% for basket weave and 15% for herringbone, where every perimeter unit is a diagonal cut.

If you set a lower allowance than the pattern justifies, the estimate says so rather than quietly under-ordering.

Random-size packs

Mixed-size packs are estimated from the coverage printed on the pack, because the size mix differs between suppliers and no calculator can predict a layout for them. The estimate says this plainly instead of inventing a plan.

Bedding

A full mortar bed is converted to sand and cement at a 1:5 ratio, using 1.6 tonnes of sand and 320 kg of cement per cubic metre of mortar.

A sand screed carries a 1.1 compaction allowance because it consolidates under the plate compactor.

Jointing

Joint volume is derived from geometry: the proportion of the surface that is joint rather than slab, multiplied by the depth of the unit.

For a 600 mm slab with a 10 mm joint that is 3.3% of the area; for a 200 × 100 mm block with a 3 mm joint it is 4.4%. Small units need proportionally more jointing material, not less.

joint volume = area × (1 − unit area ÷ module area) × unit thickness

Common questions

How many paving slabs do I need?
Divide the patio area by the module area of one slab — that is the slab size plus one joint width in each direction — then add a waste allowance for cuts. A 20 m² patio in 600 × 600 mm slabs with 10 mm joints needs 54 slabs before waste, and 60 with a 10% allowance.
How deep should a patio sub-base be?
100 mm of compacted sub-base for a pedestrian patio on firm ground, 150 mm over soft or clay subsoil, and 150–200 mm if vehicles will cross it. Remember to order roughly 30% more loose material than the compacted depth.
How much waste should I allow for paving?
5% for a straight grid on a rectangular area, 10% for most real patios, and 15% or more for herringbone, circular features or any area with angled edges.