Work out gravel, chippings and sub-base quantities by volume, weight, bags, bulk bags or tonnes — including the compaction allowance most calculators leave out.

Estimate updated. 3 bulk bags of 20 mm gravel required.

Estimate results

How this calculator works

Every figure below is derived rather than looked up, so you can check it against your own numbers. Nothing is hidden behind a black box.

Volume

Every section you add is converted to square metres, subtracted sections are removed, and the total is multiplied by the finished depth to give a volume.

volume = total area × finished depth

Compaction

Granular materials lose volume when they are compacted. If you tick the compaction option, the loose volume ordered is increased by the material's compaction factor — 1.3 for MOT Type 1 and dense graded base, 1.1 for angular chippings and sharp sand.

Skipping this is the most common reason a sub-base order comes up short.

loose volume = finished volume × compaction factor

Weight

Weight is volume multiplied by the material's loose bulk density. The engine stores a range for each material and shows it alongside the result, because moisture content alone can move the delivered weight by 10%.

weight = loose volume × bulk density

Purchase units

Bags and bulk bags are defined by weight in the UK and by volume in the US, which is why the same project produces a different pack count in each region. Loose deliveries are rounded to whole tonnes or half cubic yards to match how suppliers actually sell.

Common questions

How deep should gravel be?
40–50 mm (about 2 in) for decorative areas and paths, and 75 mm (3 in) or more for a driveway surface over a properly compacted sub-base. Going deeper than about 75 mm on a footpath makes walking harder, not better.
How many bulk bags are in a tonne?
In the UK a bulk bag is usually filled to around 850 kg despite being sold as a 'one tonne bag', so a tonne is roughly 1.2 bulk bags. Always check the filled weight with your merchant before ordering by the bag.
Why does the calculator ask about compaction?
Because a 100 mm compacted sub-base needs about 130 mm of loose material. If you order by the finished depth you will be roughly 30% short.